Learn · seo

Flooring Installation Method Statement: A Practical Guide for UK Contractors

If you're a flooring contractor or a subcontractor brought onto a managed site, you'll almost certainly be asked to produce a flooring installation method statement before work begins. Understanding what it must contain — and how it sits alongside your risk assessment — keeps your workforce safe and satisfies the client or principal contractor who requested it.

What Is a Method Statement (and What Isn't One)?

A method statement is a documented, step-by-step description of how a task will be carried out safely. It doesn't exist in isolation. In UK practice, a method statement almost always accompanies a risk assessment, and together the two documents are referred to as a RAMS (Risk Assessment and Method Statement).

The risk assessment — required under Regulation 3 of the Management of Health and Safety at Work Regulations 1999 — identifies the hazards, evaluates the likelihood and severity of harm, and records the control measures you'll put in place. The method statement then describes the actual sequence of work, referencing those controls so everyone on site understands how the job is done safely.

Neither document is a legal requirement by that precise name, but the underlying duty to assess risk and implement safe systems of work absolutely is.

When Is a Flooring Installation RAMS Needed?

You should produce a RAMS for flooring work whenever:

  • A principal contractor or client requests one (standard practice on managed sites under CDM 2015 where construction work is notifiable or involves multiple contractors)
  • The work involves significant hazards — adhesives, grinding, work in occupied premises, heavy material handling
  • Your own safe system of work requires it to demonstrate compliance

Even on smaller domestic jobs, having a documented approach protects you if something goes wrong.

What a Flooring Installation Method Statement Must Cover

A well-written method statement for flooring installation should include the following sections:

1. Project and Task Details

  • Site address, client name, principal contractor (if applicable)
  • Description of the flooring type (e.g. LVT, ceramic tile, resin, carpet, hardwood)
  • Subfloor preparation required
  • Dates and sequence of work

2. Operatives and Supervision

  • Names or roles of workers carrying out the task
  • Who holds relevant competency (e.g. CSCS card, manufacturer training)
  • Supervision arrangements

3. Plant, Equipment and Materials

  • Tools to be used: floor grinders, tile cutters, adhesive applicators, kneeling pads, levelling compounds
  • Any hired plant and its inspection status
  • Adhesives, primers, DPMs and other substances (cross-reference your COSHH assessment — see below)

4. Step-by-Step Method

This is the core of the document. Walk through the job in the order it actually happens:

  1. Site survey and subfloor assessment
  2. Removal of existing floor covering (if applicable) — including asbestos check for older buildings
  3. Subfloor preparation: grinding, levelling, priming
  4. Adhesive application and acclimatisation periods
  5. Laying, cutting, and fitting the flooring material
  6. Finishing, edging strips, sealing
  7. Curing/drying time and restrictions on access

Be specific. Vague phrases like "work safely at all times" add nothing.

5. Hazards and Control Measures

Reference your risk assessment here. Common flooring hazards include:

HazardPrimary Control
Manual handling (heavy rolls, tiles, adhesive tubs)Mechanical aids; team lifts; smaller pack sizes
Airborne dust (grinding, cutting)On-tool extraction (engineering control); RPE as last resort
Chemical exposure (adhesives, primers, solvents)COSHH assessment; ventilation; skin protection
Slips on newly laid or adhesive-coated surfacesBarriers; signage; sequenced access
Knee and back strainAnti-fatigue mats; kneelers; task rotation
Noise from power toolsQuieter equipment; hearing protection zones

Controls should follow the hierarchy: eliminate the hazard first, then substitute, engineer it out, use administrative controls, and use PPE only where residual risk remains.

6. COSHH Considerations

Many flooring products — adhesives, solvent-based primers, resin systems, DPM coatings — are hazardous substances regulated under the Control of Substances Hazardous to Health Regulations 2002. Your RAMS should reference a separate COSHH assessment for each product, confirming adequate ventilation, correct RPE (matched to the product's Safety Data Sheet), and emergency arrangements.

7. Emergency Arrangements

  • First aid provision on site
  • Nearest hospital with A&E (if working away from a fixed base)
  • What to do if adhesive fumes build up or a worker is injured

8. Sign-Off and Communication

The method statement is only useful if the people doing the work have read and understood it. Include a toolbox talk record or operative sign-off sheet so you can demonstrate that briefing took place.

Keeping It Honest and Usable

The most common failure in method statements isn't missing information — it's copy-and-paste boilerplate that bears no relation to the actual job. A principal contractor or HSE inspector will spot this immediately. Write for your specific project, your specific products, and your specific team.

Review and update the document if the scope changes mid-job — a different adhesive system or an unexpected subfloor issue may alter the risk profile entirely.

A Note on Fire Risk

If your flooring work takes place in a building where you're temporarily storing flammable adhesives or solvents, you may have duties under the Regulatory Reform (Fire Safety) Order 2005, administered by the Home Office rather than the HSE. This is separate from your RAMS and relates to fire safety management in premises — worth discussing with the building's responsible person before bringing bulk flammable materials onto site.


A thorough flooring installation method statement, paired with a proper risk assessment, protects your workers, satisfies clients, and demonstrates the professionalism that gets you rehired.

Need the document itself?

RAMSReady generates RAMS, risk assessments, method statements, COSHH and fire risk assessments to the correct published standard — or check your existing one free.

More from the RAMSReady library

Flooring Installation Method Statement: A Practical Guide for UK Contractors | RAMSReady